Road Construction Updates
700 South (2500 West to St Andrews Drive)
Underground pipes are complete. Construction is underway on the road, curb, sidewalk and driveway approaches. Construction will continue through the summer with curb, gutter, and sidewalk and new asphalt having an anticipated completion mid-August.



2500 West (700 South to 1700 South)
The north half mile of road (700 S to 1175 S) is complete. The sewer main on the south half mile (1175 S to 1700 S) is now underway. Construction will continue through the summer with curb, gutter, and sidewalk and new asphalt having an an anticipated completion mid-August.



1000 West (2700 South to Bluff) and 3300 South (1000 West to 930 West)

Pipeline installations are nearly complete. The full road width will be milled early June. The road will be reconstructed through June and new asphalt is planned in July. Roads will be closed during the day during construction and open at nights to local traffic. Please use caution and follow all signs while driving through construction zones. 



1000 West (1290 South to 1700 South)
Construction on a new waterline on the west side (southbound) of the road will be installed. Construction has begun is anticipated to continue until end of July. No parking along the west side of the road Mon-Fri 6AM to 6PM.

1290 South (1000 West to 1100 West)
Waterline installation is complete. Road construction is now underway. Completion is anticipated in July.


1025 West (1290 South to 1475 South)
Waterline installation is complete. Road construction is now underway. Completion is anticipated in July.



2700 South (500 West to 2000 West)
Construction on the sewer main re-lining will impact traffic in three cities along 2700 South. It is anticipated that impacts in Syracuse will occur beginning August and run through October. Construction will progress westward with left turn restrictions through the construction zone. There are two road closures scheduled: approx 600 West 2700 South in August, and the six-way roundabout in October. These closures will last several days. The travelling public must use caution and follow detour and construction signs. We are grateful to North Davis Sewer District for another project that will rehabilitate our sewer mains.

SR-193: State Street to 2000 West: For information on this UDOT project, use the following contacts:
Hotline: 800-948-4002
Email: sr193@utah.gov
www.udot.utah.gov/sr193
twitter.com/sr193
A recent news article indicates this will be completed by Summer 2014. News Article